Wednesday, January 9, 2013

01.09.2013 Status Update

It's been a little while since since our last post, but we have been very busy through the Holidays. Since the last update we have completed the footings in the ED area (C section), placed our foundation walls around the CEP and loading dock, and just finished the footings at the B section of the building. Our plumbing partner Rawlins has completed underground rough-ins at C area and we are prepping for our first slab pour on Monday. Everything is going very well and our next major milestone is the structural steel delivery on the 21st of this month.

Overall Site from the NE

Loading Dock Walls and the CEP


Prepping for Slab pour at the ED


Elevator Pit with Jack Holes in place


Freshly poured footing in B Section