Check out our updated aerial photos, we are making a lot of progress and will start install the skin of the building in the next couple of weeks. The ED section of the building is almost completely roughed in and we have placed our last elevated slab yesterday. The project is now just past its midway point and we don't plan on slowing down anytime. All those passing by on the surrounding roads please take note that we will begin the road widening process next week which will take about 2 months.